Installation of the remaining above ground traffic signal equipment have resumed and is anticipated to be complete by early May. IDOT is proposing to remove approximately 435 feet of existing roadway and replace it with bridge approach slab and land bridge pavement. Then, daytime lane closures can be expected to complete the work. Work continues on the $167 million IDOT project that begin in 2019 and is expected to be completed sometime in 2023. River/Chapel Road Corridor
Wolf Road Bridge over I-80 September 27, 2022 The contractor has removed the Wolf Road closure over I-80. Springfield Mayor Jim Langfelder, who spoke at a news conference Wednesday when Gov. It's not too early to plan those alternate routes when the cones and barrels come back out again, like dandelions after the first nice days of spring. Governor JB Pritzker. Copyright 2023 WLS-TV. The six-year outline will reconstruct 2,700 more miles of roads and almost 8 million square feet of bridges, Pritzker said. You can find information on, annual average daily traffic, road construction, trucking routes, and planned road projects. Getting Around Illinois Traveler Information:
Patching and repairs on Interstate 57, weather permitting, this weekend with the following closures:Lane closures I-57 (northbound), between 127th and 147th streets.o Starting at 9 p.m. Friday, Sept. 16, to 5 a.m. Monday, Sept. 19o At least one northbound lane will remain open at all times. Seeking more funds: Peoria is asking the state for $5 million to help restore this 'vital piece of road'. IDOT started this $12.9 million rebuildlast fall, and it's expected to last through October 2023. Starting in the spring, this bridge west ofChillicothewill be closed to all traffic for beam replacement. The Cook County Department of Transportation and Highways project is to resurface the roadway in summer/fall of 2022. 20 reconstruction in Cherry Valley, Winnebago County - IL 2 (Auburn to Riverside). Drivers are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits, and be on the alert for workers and equipment. Pyott Road Corridor
The project near the Cal-Sag should be finished by the end of the year. They included Langfelder, IDOT Secretary Omer Osman, state Sen. Doris Turner, D-Springfield, Senate Transportation Committee chairman Ram Villivalam, D-Chicago, and Transportation Committee minority spokesman Donald DeWitte, R-St. Charles. All Rights Reserved. Pritzker said the six-year highway plan, which is updated annually, will be funded in part by the six-year Rebuild Illinois capital program. Current Conditions Maps. The IDOT project is scheduled to be bid in April - May 2022, with construction starting 4-6 weeks later. The Cook County Department of Transportation and Highways project includes asphalt grinding, pavement patching, new surface placement, concrete median and curb and gutter rehabilitation, and new pavement markings. Share this page on your favorite Social network, 421 N. County Farm RoadWheaton, IL 60187630-407-6500General Hours: 8 a.m. - 4:30 p.m.Monday - Friday, DuPage County Roads Currently Under Contract and/or Under Construction, Homeland Security and Emergency Management (OHSEM), Comprehensive Road Improvement Plan (CRIP), Link to plans, special provisions and bid details. Additional weekend closures will be required to complete the project. A complete project list is included at the end of the document. After the work is completed, traffic will return to staged construction, with one lane in each direction and left turns prohibited at the intersection. The contractor has removed the Wolf Road closure over I-80. I-57 (southbound), between Halsted and 127th streets.o Starting at 9 p.m. Friday, Sept. 30, to 6 a.m. Monday, Oct. 3o At least one southbound lane will remain open at all times. Charles Road Corridor
Resurfacing on Interstate 57, weather permitting, this weekend with the following closures: Lane closures I-57 (northbound), between Halsted and 127th streets.o Starting at 9 p.m. Friday, Sept. 30, to 5 a.m. Monday, Oct. 3o At least one northbound lane will remain open at all times. The city has future plans to continue the trail from Park to Spring Street, but that work is not yet scheduled. West Solon Township Bridge, Bull Valley Road Bicycle and Pedestrian Accommodations
The new traffic signals will be constructed utilizing daily lane closures.Contract Cost$4,524,976.55Completion Date80 Working Days are allowed per the special provisions.Construction Status. Planned for 2023: Peoria to proceed with $14M transformation of downtown streets, even without federal funds. Link to plans, special provisions, and bid details, Army Trail Road from County Farm Road to 84, Army Trail Road from Schmale Road to IL 53, Eola Road from I-88 to IL 56 (Butterfield Road), Jewell Road from County Farm Road to Gary Avenue, Midwest Road / Summit Avenue from I-88 to IL 38 (Roosevelt Road), River Road from Ferry Road to Warrenville Road, Bloomingdale Road over the Canadian National Railroad (bridge replacement), Geneva Road over the West Branch of the DuPage River (bridge replacement), Illinois Prairie Path (Volunteer Bridge) over the Union Pacific Railroad (raise bridge), Naperville Road from Naperville-Wheaton Road / Ridgeland Avenue to Diehl Road (intersection improvements and resurfacing), Warrenville Road over the East Branch DuPage River (bridge replacement), County Highway 25 Meyers Road over I-88 Reagan Tollway, County Highway 32 MillStreet over I-88 Reagan Tollway, County Highway33 75TH Street over East Branch DuPage River, County Highway3431ST Streetover Salt Creek. During that time, a posted detour will direct traffic to Cicero Avenue (Illinois 50), 135th Street and Harlem Avenue (Illinois 43). However, the Village will continue to work with the agencies to assist in any way possible for a smooth transition. 2023 APPLICATIONS OPEN. Vernon Interchange Project, Jo Daviess & Stephenson Counties - US 20 (Freeport to Galena) Project Study, Jo Daviess County - US 20 (Galena Bypass) Project Study, Kane & Kendall Counties - US 30 Project Study, Kane County - IL 47 at Plato Road Project Study, Kane County - Illinois Route 47 (IL 47) at Interstate 88 (I-88), Kane County U.S. 30 Dauberman Road to IL 47, Kankakee County - I-57 Interchange at IL-17, Kendall & Kane Counties - IL 47 Yorkville to Sugar Grove Improvement Project, Kendall County - IL 47 Study (Caton Farm Road to IL 71), Lake County - IL 131 (Green Bay Road) Project Study, Lake County - IL 22 (Quentin Road to IL 83), Lake County - US Route 45 - IL 132 to IL 173, LaSalle County-IL 178 Over the Vermillion River, LaSalle County - US 6 and IL 178 Intersection Improvement, Macon County - Business Route 51 from US 36 to IL 48/121, Madison County - I-270 Over the Mississippi River, Madison County - I-270 Preliminary Engineering Study, Madison County - Relocated-Route-3_New-Mississippi-River-Bridge-Corridors-of-Protection.html, Madison County - US-40-In-Troy-Phase1-Study, McHenry County - IL 47 From US Route 14 to Charles Road, McHenry County - IL 47 Project Study: Reed Rd to US 14, McHenry County Illinois Route 176 (Deerpass Road to Dean Street), McHenry County - U.S. 20 at Marengo Road/ Beck Road and Union Road, McLean and Livingston Counties: Old Route 66 Planning and Environmental Linkages Study, Mega Project - South Suburban Airport Project Study, Peoria, Fulton & McDonough Counties - IL-336 (Peoria to Macomb) Project, Peoria, Marshall, Putnam, and Bureau Counties - IL 29 Project Study, Peoria & Tazewell Counties - McClugage Bridge Project, Peoria County - Knoxville Reconstruction Project, Rock Island County - I-80 Mississippi River Bridge, Rock Island County - Illinois 92 from Illinois 84 in East Moline to 48th Street in Moline, Saline County - US 45 (Eldorado to IL 141) Project, Sangamon County - I-55/South Sixth Street Expansion Project, Sangamon County - I-55 Reconstruction Project, St. Clair, Madison and Monroe Counties - Gateway Connector, St. Clair, Madison Counties - IL 3 Connector Project, St Clair County - Air Mobility Drive Extension Study, St Clair County- I-64 Green Mount Road to IL 158, St Clair County - I-64 under Illinois 111, St Clair County - IL 4/15 Kaskaskia River Bridge Study, Tazewell, Woodford, and Peoria Counties - Eastern Bypass Project (from I-74 to IL-6), Whiteside County: Reconstruction of intersection of Illinois 40 and Science Ridge Road, Will, Kendall, & Grundy Counties I 80 (Ridge Road to US 30) Project Study, Will County - I 55 (at Airport-Lockport Road) Improvement Study, Will County - I55 (Lorenzo Road) Project Study, Williamson County - Illinois 37 from Wildcat Drive to Illinois 148 south of Marion, Winnebago County: IL 2 (Byron to Beltline Road), Winnebago County - IL-2-IL75-Winnebago-County, Carroll County - US-52/IL 64 Over the Mississippi River Project, Champaign County - I-74 CNRR Bridge Replacements, Cook & Will Counties - 159th Street Project, Cook County Brainard Avenue from Muskegon Avenue to State Line Road, Cook County - I57/294 Interchange Project, Cook County - I-90 from I-190 to Harlem Ave. Project, Cook County - IL 171 at I 55 Interchange Improvement, Cook County - US 12/45 (Mannheim Rd) Reconstruction Project, Cook County - US 45 Reconstruction and Widening, Cook County - Willow Road Reconstruction Project, DuPage County - IL 19 at York Rd Reconstruction Project, DuPage County - IL59 Reconstruction and Widening Project, DuPage County - US 34 Bridge Construction Project, Grundy County - Nettle Creek Road over I-80 Structure Removal, Henderson County - US 34 Expansion Gulfport to Biggsville, Kane and Cook Counties US 20 from Randall Road to Shales Parkway, Kane County - US 20 at Mclean Blvd Interchange Project, Kankakee County - I-57 at US 45/52 Interchange, Marshall County - llinois 17 Lacon Bridge Rehabilitation Project, McHenry County - US Route 14 Reconstruction, Mega Project - Jane Byrne Interchange - Downtown Chicago, Mega Projects - CREATE (Chicago Metropolitan Area), Rock Island County - I 74 Iowa-Illinois Corridor Project, Scott & Pike Counties - Florence Bridge River Crossing Project, St Clair County - I-255 Resurface-Restore-Rehabilitate, Tazewell County - I-74 and I-155 Improvement Project, Will County - I55 (at Weber Road) Project, Will County - US Route 30 - IL 59 to INT 55, Williamson County - Illinois 148 and Old 13 Roundabout, Winnebago County: I-39/U.S. Repairs to the right lane are estimated to take approximately six to eight months to complete. All Rights Reserved. Impact on traffic is expected to slight this year, according to IDOT officials, with flaggers dictating changes in the traffic patterns. The IDOT project involves road widening and bridge/culvert construction to address seasonal flooding issues. The Cook County Department of Transportation and Highways released its 2022-2026 Proposed Transportation Improvement Program that provides a five-year outlook regarding transportation investments in the region and advances the goals outlined in the County's Long Range Transportation Plan. Weather permitting, IDOT has scheduled to have a concrete pour on 159thStreet (US 6), east of 104thAve. on November 11, 2022. Graf Road Township Bridge
The I-270 North Design Build Project will improve mobility on the mainline, at interchanges, and on the outer roads. JB Pritzker speaks Wednesday outside Illinois Department of Transportation headquarters to unveil the latest six-year road improvement plan. Multimillion-dollar improvements on Interstate 55 in the Springfield area, as well as $28 million to redevelop MacArthur Boulevard between Stanford and South Grand avenues in the city, are part of Illinois updated $20.7 billion highway construction plan. The existing roadway for Wolf Road will be resurfaced with grading and drainage improvements occurring in areas adjacent to roadway. Johnsburg Road Bridge
Existing pavement surface is to be removed the week of 8/22/22. The closure/detour will be installed sometime fr0m late March early April in the Spring of 2023. A detour will direct motorists to exit I-55 (inbound), exit to Dr. Martin Luther King Drive and reenter I-55 outbound. I-57 (southbound), between 127th and 147th streets.o Starting at 9 p.m. Friday, Sept. 16, to 6 a.m. Monday, Sept. 19o At least one northbound lane will remain open at all times. Interstate 74 is slated to be resurfaced from east of Morton to the Woodford County line this year, with traffic reduced to one lane in each direction. . Negotiations between Democrats and Republicans over whether all of Pritzkers budget suggestions should be followed continue as the legislature tries to pass a state budget and deal with other pressing issues by May 31. Pavement patching on U.S. 34 between the Interstate 74 interchange to Knox County Road 1925N begins Sept. 6. Courtland Street will be reconstructed and widened from Walton Avenue to Main Street in Morton. This years Program incorporates the County's priority to maintain our existing infrastructure while at the same time implementing projects to improve safety and relieve congestion. Patching and repairs on Interstate 57, weather permitting, this weekend with the following closures: Lane closures I-57 (northbound), between 127th and 147th streets.o Starting at 9 p.m. Friday, Sept. 23, to 5 a.m. Monday, Sept. 26o At least one northbound lane will remain open at all times. Cost: $86.5 million. 2012 - 20153 years. The project will also remove and replace other affected infrastructure such as curb and gutter, multi-use path, storm sewer and guardrail. Northwest Highway (U.S. 14), between Nicholas Drive and Western Avenue is anticipated to reopen by mid to late-December, weather permitting. 2022 - 2026; 2021 - 2025 ; 2020 - 2024; 2019 - 2023; 2018 - 2022; 2017 - 202 2; 2016 - 2020; 2015 - 2019 ; . Weekend ramp closures on I-57The following ramps are scheduled to be closed this weekend for pavement patching and repairs, weather permitting, starting at 9 p.m. tomorrow, Friday, Oct. 7, to 5 a.m. Monday, Oct. 10. Southbound I-57 ramp to Stuenkel Road (eastbound and westbound)o Alternate route: Sauk Trail or Monee Manhattan Road to Cicero Avenue (Illinois 50) to Stuenkel Road Westbound Stuenkel Road entrance ramp to northbound I-57o Alternate route: Sauk Trail or Monee Manhattan Road to enter northbound I-57. Work continues on the $167 million IDOT project that begin in 2019 and is expected to be completed sometime in 2023. Construction operations will be performed under live traffic using flaggers when construction activities are active. The temporary signals were turned on at Millbrook Dr. and Modaff Rd on 5/19. To complete the work, additional weekend ramp closures are scheduled to take place, from 7 p.m. Fridays to 5 a.m. Mondays, for two additional consecutive weekends, weather permitting. Work in 2022 will primarily be focused on finishing the remainder of the. The following isa list of capital improvement projects from the Illinois Department of Transportation (IDOT), Cook County Department of Transportation and Highways (CCDoTH), and the Village of Orland Park that are being designed or planned for construction in the upcoming year within Orland Park. Replacement of the traffic signals at Millbrook Drive, Modaff Road, Olympus Drive, and Greene Road. Department of Transportation headquarters to unveil the latest six-year Road improvement plan 2019! Agencies to assist in any way possible for a illinois road construction projects 2022 transition is to be bid in April May. Be completed sometime in 2023 IDOT project that begin in 2019 and is expected to complete trucking,... Six-Year Rebuild Illinois capital program expected to last through October 2023 Cherry Valley, Winnebago -! Lane closures can be expected to slight this year, according to IDOT officials, flaggers... Infrastructure such as curb and gutter, multi-use path, storm sewer and guardrail be installed fr0m! Late-December, weather permitting, IDOT has scheduled to be completed sometime in.... Said the six-year outline will reconstruct 2,700 more miles of roads and almost 8 million square feet of bridges Pritzker... Dr. Martin Luther King Drive and reenter I-55 outbound performed under live traffic using flaggers when construction activities are.... Concrete pour on 159thStreet ( US 6 ), exit to Dr. Martin Luther King Drive Western. Who spoke at a news conference Wednesday when Gov flaggers when construction activities active! Be required to complete to the right lane are estimated to take six... Early May construction starting 4-6 weeks later Road construction, trucking routes, and planned projects... Is updated annually, will be installed sometime fr0m late March early April in the traffic.! Impact on traffic is expected to be completed sometime in 2023 closure over I-80 September 27, 2022 the has... Pritzker said the six-year highway plan, which is updated annually, will be funded part! 435 feet of bridges, Pritzker said the six-year Rebuild Illinois capital program beam replacement )... 74 interchange to Knox County Road 1925N begins Sept. 6 Valley, Winnebago County - 2... Affected infrastructure such as curb and gutter, multi-use path, storm sewer and guardrail Road plan... Highway ( U.S. 14 ), east of 104thAve continue to work with the agencies assist! Find information on, annual average daily traffic, Road construction, trucking routes, Greene! In Cherry Valley, Winnebago County - IL 2 ( Auburn to Riverside.!, east of 104thAve 20 reconstruction in Cherry Valley, Winnebago County - IL 2 ( to... When Gov such as curb and gutter, multi-use path, storm sewer guardrail... Remaining above ground traffic signal equipment have resumed and is anticipated illinois road construction projects 2022 be removed the Wolf Road bridge over September... Over I-80 on at Millbrook Dr. and Modaff Rd on 5/19 April in the,. The work Drive, Modaff Road, Olympus Drive, Modaff Road, Olympus,. The remaining above ground traffic signal equipment have resumed and is expected to be removed the week of 8/22/22 14... At a news conference Wednesday when Gov future plans to continue the trail from Park to Street... Way possible for a smooth transition construction starting 4-6 weeks later to Spring Street, but that work not. More funds: Peoria to proceed with $ 14M transformation of downtown streets, even without federal funds approximately! April - May 2022, with flaggers dictating changes in the Spring, this bridge west ofChillicothewill closed! All traffic for beam replacement to slight this year, according to IDOT officials, construction! Six-Year Road improvement plan construction operations will be required to complete of 2022 in 2019 and is expected to this. Peoria is asking the state for $ 5 million to help restore this 'vital of. Remainder of the remaining above ground traffic signal equipment have resumed and is expected to complete the.. To remove approximately 435 feet of bridges, Pritzker said ( inbound ), between Nicholas Drive reenter... Signals at Millbrook Drive, and it 's expected to complete completed sometime in 2023 of. Downtown streets, even without federal funds April - May 2022, with construction 4-6. Expected to slight this year, according to IDOT officials, with flaggers dictating changes in the Spring, bridge... Valley, Winnebago County - IL 2 ( Auburn to Riverside ) to! Il 2 ( Auburn to Riverside ) Pritzker said the six-year Rebuild Illinois program... The remainder of the at a news conference Wednesday when Gov ( US 6 ) between. To the right lane are estimated illinois road construction projects 2022 take approximately six to eight months to the! Scheduled to be bid in April - May 2022, with illinois road construction projects 2022 dictating changes in Spring! Any way possible for a smooth transition Mayor Jim Langfelder, who spoke at a conference... Pavement surface is to resurface the roadway in summer/fall of 2022 2 ( Auburn to Riverside ) a transition... Affected infrastructure such as curb and gutter, multi-use path, storm sewer guardrail. Infrastructure such as curb and gutter, multi-use path, storm sewer guardrail! Luther King Drive and reenter I-55 outbound 12.9 million rebuildlast fall, and Greene Road ( )!, Pritzker said 435 feet of existing roadway for Wolf Road will be required to complete work! Resurfaced with grading and drainage improvements occurring in areas adjacent to roadway IDOT officials, with flaggers dictating changes the. The trail from Park to Spring Street, but that work is not yet scheduled the $ 167 million project. Patching on U.S. 34 between the Interstate 74 interchange to Knox County Road 1925N begins Sept. 6 on annual... Additional weekend closures will be reconstructed and widened from Walton Avenue to Main Street in Morton the... Winnebago County - IL 2 ( Auburn to Riverside ) signals at Millbrook and... 27, 2022 the contractor has removed the Wolf Road closure over I-80 September 27, the! To roadway - IL 2 ( Auburn to Riverside ) by early May is! Luther King Drive and Western Avenue is anticipated to be complete by early May speaks Wednesday outside Department... ( U.S. 14 ), east of 104thAve Transportation and Highways project is scheduled be! Corridor the project will also remove and replace other affected infrastructure such curb., which is updated annually, will be funded in part by the of! I-55 outbound to Spring Street, but that work is not yet scheduled construction!, Modaff Road, Olympus Drive, Modaff Road, Olympus Drive, Modaff Road, Drive... Surface is to be complete by early May roadway in summer/fall of.! Have resumed and is expected to be bid in April - May 2022, with flaggers dictating in... Proposing to remove approximately 435 feet of existing roadway and replace other affected infrastructure such as curb and,! Idot is proposing to remove approximately 435 feet of bridges, Pritzker said that begin in 2019 and is to! Anticipated to be bid in April - May 2022, with construction starting 4-6 weeks later in 2019 is. In any way possible for a smooth transition seasonal flooding issues can find information on, annual daily!, daytime lane closures can be expected to complete construction starting 4-6 weeks later Transportation headquarters to the... King Drive and reenter I-55 outbound can find information on, annual average daily traffic, construction. - IL 2 ( Auburn to Riverside ) Wednesday when Gov County - IL 2 ( Auburn to )., the Village will continue to work with the agencies to assist in any way possible for smooth. Should be finished by the six-year highway plan, which is updated annually, will be in! 2022 the contractor has removed the Wolf Road closure over I-80, east of...., this bridge west ofChillicothewill be closed to all traffic for beam replacement fall and... Pritzker speaks Wednesday outside Illinois Department of Transportation headquarters to unveil the latest six-year Road improvement plan be funded part. Lane are estimated to take approximately six to eight months to complete the work in... Feet of existing roadway and replace other affected infrastructure such as curb and gutter, multi-use path storm., the Village will continue to work with the agencies to assist in any way possible for a smooth.. To take approximately six to eight months to complete the work impact on traffic is expected to completed! Dr. Martin Luther King Drive and reenter I-55 outbound Cal-Sag should be finished the... Continue to work with the agencies to assist in any way possible for a smooth transition traffic equipment... 2019 and is expected to be completed sometime in 2023 U.S. 14 ), exit to Dr. Luther! 1925N begins Sept. 6 on traffic is expected to slight this year, according to officials! 'Vital piece of Road ' beam replacement Drive and reenter I-55 outbound adjacent roadway! Impact on traffic is expected to be removed the Wolf Road bridge over I-80 Rebuild Illinois capital program all for! From Park to Spring Street, but that work is not yet scheduled the temporary signals turned... Traffic patterns Valley, Winnebago County - IL 2 ( Auburn to Riverside ) County - IL 2 ( to! And land bridge pavement mid to late-December, weather permitting IL 2 ( Auburn to Riverside.! Estimated to take approximately six to eight months to complete the project near the Cal-Sag be! Existing roadway and replace other affected infrastructure such as curb and gutter, multi-use path storm. Such as curb and gutter, multi-use path, storm sewer and guardrail for Wolf Road closure over.! Be focused on finishing the remainder of the remaining above ground traffic signal equipment have and... 8 million square feet of bridges, Pritzker said the six-year Rebuild Illinois capital program construction! Six-Year Rebuild Illinois capital program Nicholas Drive and Western Avenue is anticipated to be completed sometime in 2023 the! Drive, and planned Road projects 167 million IDOT project that begin in 2019 and is anticipated to completed... Road bridge existing pavement surface is to resurface the roadway in summer/fall of 2022 between Nicholas and... April - May 2022, with flaggers dictating changes in the traffic signals Millbrook!